projects - water + sanitation

project name Dubai Pearl
utilities and services design
owner Pearl Dubai FZ LLC, Dubai (U.A.E.)
architect Schweger & Assozierte, Hamburg (Germany)
mep consultant Ebert Ingenieure, Munich (Germany)
location Dubai (U.A.E.)
project duration

begin november 2007
end january 2008

  print or save project sheet

Dubai Pearl is an urban development on an important location landward to famous “Jumeirah Palm Island”. The project consists of a central high rise complex of four towers of 260 m (850 ft) and a surrounding living city.

total constructed area 1.394.052 m² (15 Msft)

panoramic view Dubai pearl seaward ©schweger assoziierte, hamburg (germany)

responsibilities

schematic design and master plan for utilities and public services:

  • water supply, including water mains, pumping station, water storage tanks 5,000 m³ (1.3 Mgal), greywater reuse network
  • sewage system, wastewater collection and treatment for greywater reuse
  • stormwater drainage chilled water distribution for 125 MW (117 MBTU/s)
  • chilled water demand, up to DN 1500 (60 in) chilled water mains
  • utilities and service tunnel for pipe and cable works

panoramic view Dubai pearl landward ©schweger assoziierte, hamburg (germany)